Infilling of wind farm cable ducts
Bentonite (Manufacturing & Supply) Ltd was asked to infill three cable ducts with diameters of 800mm with a 250mm cable insert for wind farms located in the North Sea off Cleethorpes for AMS No-Dig and Orsted energy. The material used for this particular project was Cebo 2.0 conduct gel, which was delivered by tankers to fill our on-site silos for our automated batching machine.
- Project information: AMS No-Dig/Orsted, North Cotes, Cleethorpes.
- Date: August 2021.
- Total volume for project: 260m3.